Summary not yet generated for this topic.

Community sentiment

Concerned (1)

At a glance

Public comments
1
Last 30 days
0

Last discussed Apr 6, 2026.

Public comments (1)

ConcernedBrian DesFossesApr 6, 2026

Public Works urged an 8-inch sewer line even under 2,000 gallons/day to avoid expensive future replacement, noted DOT permitting of the state-road access, flagged a possible grease trap if a cafeteria is added, and warned about trucks misusing the 10-foot loading area with its narrower 22-foot aisle.

Planning Board - Apr 6, 2026 · 0:00 →