Summary
The developer has spent six months trying to get National Grid to respond about the 1920s-era power line easement running through the site. The board kept the condition but moved it to before occupancy, letting construction start while talks continue.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Apr 20, 2026.
Impact analysis
The delay has blocked the developer from obtaining building permits, pricing, and contractor scheduling.
The developer can now price, schedule and start construction while pursuing the utility agreement.
If an easement dispute arises after units are sold, future homeowners and the condo association could inherit the problem.